Each box is an activity; the number it contains is the duration of the activity
Each box is an activity; the number it contains is the duration of the activity in days. The duration of the critical path is(75)
A.16days
B.14days
C.19days
D.20days
正確答案:C解析:關鍵路徑為最長時間的線路,3+6+7+1+2=19。
詞條內(nèi)容僅供參考,如果您需要解決具體問題
(尤其在法律、醫(yī)學等領域),建議您咨詢相關領域?qū)I(yè)人士。